KAVODA Project status

Phase 0 — Foundations Done

Repo, CI, event schema, migrations, test harness, release versioning.

Phase 1 — Content readiness In progress

QC, packaging, encryption, delivery, and ingesting the real catalogue.

Phase 2 — Backend services Done

Events, feed, auth, entitlements.

Phase 3 — Roku app In progress

The backend side of the Roku launch build (the app itself lives in the frontend repo).

Phase 4 — Compliance, certification and launch Planned

Drills, load test, Roku certification, launch checklist.

Side tasks

Login page brand styling Done 2026-10-12 Social sign-in buttons are behind flags and currently off.
Second supplier batch ingest In progress
Post-MVP backend In progress
  • Watch progress (resume where you left off) In progress
  • Catalogue fields In progress
  • App settings and access gate In progress
  • Metadata enrichment In progress
  • Roku integration docs In progress
Server-driven UI Planned
Project status page (status.kavoda.tv) Done 2026-10-14